May 2, 2019–May 8, 2019
201930 Sprint 8
Sprint 8 Goals:
Senior Project Lessons Learned Presentation, May 8th
Deliver Working System to Client and get sign-off, May 8th
Discovery:
- Resolve bottlenecked issues and merge requests
- Archival/Retrieval
- CATME Integration (Web)
- Continue documenting prod upgrades (prometheus, grafana, telegraf, etc)
- Document process to address prod issues
Delivery:
- Upgrade non-CentOS machines (ada, grading, hopper, maven)
- Continue resolving production issues with Delvin
- Further test all scripts for system deployment/teardown, and run in a daily cycle